Bathroom Renovation Project
EXECUTIVE SUMMARY
- Construct durable bathroom facilities to match the high traffic requirements
- Increase bathroom count to match required capacity ratios
- Provide financial accountability to the donors
- Provide visibility and transparency throughout the various project stages
- Deliver project in an acceptable timeframe
- Deliver project within the budget
- Provide adequate security measures to prevent theft once completed
- Work with the school to establish policies and operating procedures to handle vandalism
- Work with the school to establish maintenance plan for day to day operations
- Meet all necessary ADA and other local compliance requirements
- Align project with CC master plan
Project Scope:
Phase 1 - Nineth (9th) Grade Block. (Upper and Lower)
Phase 2 - Pending feedback from the CC Master Plan
Project Estimates:
Funding for the Cornwall College bathroom renovation project is primarily obtained from donations by the general CC community. Please join us in the rebuilding effort by donating to Gofundme.com/rebuildcc. Initial estimates via the gofundme campaign to improve and expand the facilities is approximately $50,000 USD. Official estimates will be shared following the architectual designs and reviews.
- High Level Estimate $50,000 USD
- Source of funds - raised via Gofundme.com/rebuildcc (Click to support)
- Estimate for Sanitary Fixtures Estimates_From_Fergusion_Enterprise.pdf
- Completed Bill of Quantity Estimate -
- Estimate from the National Water Commission Estimate_from_National_Water_Commission.jpg
- Payment Schedule -
Project Design
Our local team in Montego Bay is currently working on delivering the architechtural design. The initial review of the first draft was reviewed on January 24th, 2019.
- Draft design submitted 1/24/2019 - 9th Grade Block - Lower Level
- Updated Draft submitted 2/14/2019 - 9th Grade Block - Upper & Lower level
Project Team
The core project team consist of a combined effort from both the South Florida and the Montego Bay chapter members. All efforts are 100% volunteer.
Name | Chapters / Affiliates |
Kimani Phillips | South Florida |
Warren Bloise | South Florida |
Patrick Green | South Florida |
Orville Denton | South Florida |
Garth Brown | Montego Bay |
Kevin Rosegreen | Montego Bay |
Rudal MacFarlane | Montego Bay |
Project Schedule & Timeline:
The projected high-level timeline is to compete the project for the upcoming 2019 Fall (September) semester.
Date (Month) | Project Actvities |
December | Planning |
January | Design Concepts |
February | Finalize Design Concepts & Cost Projections |
Stakeholder review and Approval | |
March | RFP (Request for Pricing) Proposals |
April (On Schedule) | Contractor Selection |
May | Initiate Procurement Activities |
July (1st) | Implementation |
July (31st) | Project Closure |
Project Closure:
- Completed Project (Pics & Videos) - Coming soon
Contact Us:
Please feel free to share any feedback, questions or concerns with the team via the following email address This email address is being protected from spambots. You need JavaScript enabled to view it.